Mossmorran pledge on flaring over Christmas – Auto Republish

Mossmorran pledge on flaring over Christmas

Reported by:

Original Source: Source link

The operators of Mossmorran have publicly promised to avoid flaring during the Christmas holidays.

The Fife Ethelyne Plant has been shut down since August following explosions at two of its boilers.

It originally envisaged de-activating for a few weeks, but this was extended until towards the end of 2109 to complete a major “repair and replace” programme of work.

You may also be interested in:

Woman seriously injured crossing Fife road

Pub plan revealed for landmark Kirkcaldy building

Armed police at Fife bus station

In a briefing to the community, the plant’s managers said they were now updating their schedules to relaunch the plant.

Jacob McAllister, manager, said: “Our planning has always included a commitment that we will avoid flaring during the Christmas period of 24-26 December.

“It is currently projected that the main phase of re-start will commence after that.”

The operators said they were working with regulators on their plan to re-start the plant.




Source link

Leave a Reply

Your email address will not be published. Required fields are marked *

Resident-led action group seeking redress from the long-term social, health and environmental impacts from the Mossmorran facilities in Central Fife operated by ExxonMobil (Fife Ethylene Plant) and Shell (Fife NGL).

Contact

Press Inquiries

Scroll to Top